Renewable Energy Projects

ELEMKA has significant experience in the field of Renewable Εnergy, with several wind park projects and geothermal applications. The company undertakes the construction of all the infrastructures of the Wind Parks, including the earthworks and concrete works from the initial stage of the project. The Parks are delivered ready for the installation of the wind turbine pylons.

ELEMKA provides reliable services in geothermal installations in buildings and industry. Α complete package of services and products related to geothermal applications is provided, which includes the design and the licensing of the installation and operation, the design of heating and air conditioning facilities served by the system, the supply of the required equipment, the commissioning and the maintenance services.

Wind Park “MAKRYNOROS” 43.2 MW

Location: Nafpaktos, Greece
Execution Period: September 2020 - In Progress
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Wind Generators)
Number and type of WT: 12 Wind Generators of 3,6MW each – VESTAS
Total Power: 43.2 MW
Owner: MAKRYNOROS S.A.
Construction: ELEMKA S.A.

Wind Park ‘’POUNTA’’ 11.0 MW

Location: Kymi, Evia, , Greece
Execution Period: May 2019 - June 2020
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Wind Generators)
Number and type of WT : 2 Wind Generators of 0,9MW each – E44 ENERCON & 4 Wind Generators of 2,3MW each - ENERCON
Total Power: 11.0 MW
Owner: AIOLIKI EVIAS POUNTA S.A.
Construction: ELEMKA S.A.

Wind Park ‘’HELONA’’ 8.1 MW

Location: Karystos, Evia, Greece
Execution Period: September 2018 - March 2019
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Wind Generators)
Number and type of WT: 9 Wind Generators of 0,9MW each – E44 ENERCON
Total Power: 8.1 MW
Owner: AIOLIKI EVIAS HELONA S.A.
Construction: ELEMKA S.A.

Wind Park ‘’DIAKOFTIS’’ 11.7 MW

Location: Karystos, Evia
Execution Period: June 2018 - March 2019
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Wind Generators)
Number and type of WT: 13 Wind Generators of 0,9MW each – E44 ENERCON
Total power: 11,7 MW
Owner: AIOLIKI EVIAS DIAKOFTIS S.A.
Construction: ELEMKA

Wind Park ‘’PYRGOS’’ 15.3 MW

Location: Karystos, Evia, Greece
Execution Period: June 2017 - April 2018
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Wind Generators)
Number and type of WT: 17 Wind Generators of 0,9MW each – E44 ENERCON
Total power: 15.3 MW
Owner: AIOLIKI EVIAS PYRGOS S.A.
Construction: ELEMKA S.A.

Wind Park ‘’PETALAS’’ 48.0 MW

Location: Petalas Amfilochias, Aitoloakarnania, Greece
Execution Period: May 2017 - April 2018
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Vestas V100 WT Wind Generators)
Number and type of WT: 24 Wind Generators of 2.0MW each – V100 Vestas WT
Total power: 48 MW
Owner: SPIDER S.A.
Construction: ELEMKA S.A

Wind Park ‘’ANEMOMYLOS’’ 12.0 MW

Location: Akrefnio, Viotia, Greece
Execution Period: May 2016 - December 2016
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Vestas V100 WT Wind Generators)
Number and type of WT: 6 Wind Generators of 2.0MW each – Vestas V100 WT
Total power: 12 MW
Owner: PROTERGIA S.A.
Construction: ELEMKA S.A.

Wind Park ‘’ADERES’’ 4.0 MW

Location: Aderes, Argolis, Greece
Execution Period: January 2016 - February 2016
ELEMKA's Scope: Foundation construction of 2 Wind Generators
Number and type of WT: 2 Wind Generators of 2.0MW each – E-92 ENERCON WT
Total power: 4.0 MW
Owner: BUSINESS ENERGY S.A.
Construction: ELEMKA S.A.

Wind Park ‘’KORYFI’’ 15.0 MW

Location: Sidirokastro, Serres, Greece
Execution Period: October 2015 - July 2016
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Vestas V100 WT Wind Generators)
Number and type of WT: 5 Wind Generator of 3.0MW each – Vestas V100 WT
Total Power: 15.0 MW
Owner: AIOLIKI SIDIROKASTROU S.A.
Construction: ELEMKA S.A.

Wind Park ‘’AGKISTRO’’ 23.1 MW

Location: Agkistro, Serres, Greece
Execution Period: October 2015 - June 2016
ELEMKA's Scope: Design and Construction of Wind Park Civil works (Access Road Network, Excavations and Foundation of Vestas V112 WT Wind Generators)
Number and type of WT: 7 Wind Generators of 3.3MW each – Vestas V112 WT
Total power: 23.1 MW
Owner: AIOLIKI ANDROU TSIROVLIDI S.A.
Construction: ELEMKA S.A.